 Completion period will be 5 to 6months from date of approval and advance received
 Drinking water, Construction Water and EB for Construction works to be arranged from client side
 Rates/ prices / Qty’s for the above broad scope works including Material & Labor, if any varies in Qty, cost also will vary
 Payment to be released within 2 days from date of bill submitted
 Additional works if any informed by client to be paid extra
 Electrical fittings fixing works will not be in our scope
 Interior works will not in our scope
 Normal isolated Foundation only considered
 Quoted rates is valid for 15 days from the date of estimate given
 As GST is not considered, Amount to be Paid by cash of transferred in Savings account

Payment stages

o As per annexure

Extra works apart from main building built up area as below

  • EB / metro water/ drainage connection – dept works
  • Interior wood works
  • Temporary EB supply
  • Special Elevations
  • Electrical fittings fixing